0. Verdict and what changed

Agree with the direction; ten changes before it is pilot-ready. v0.1 is a sound delivery and forecasting framework. It is not yet a framework for the bottleneck it names: it treats planning as a cost to cut, while the thesis says deciding what to build is the scarce input. v0.2 fixes that tension and adds what 2025–2026 research shows about where AI gains actually disappear.

#ChangeWhySection
1Split "planning" into coordination, decision and proofThe thesis and the Planning Budget pull in opposite directions1
2Planning Budget becomes the Decision Budget, with a new Build-to-decide modeCheap building is now the cheapest discovery tool; v0.1 only allows spikes6
3Every bet carries an outcome hypothesis and a kill criterionv0.1 proves delivery, but nothing forces the team to learn whether the outcome moved5
4The spec becomes durable agent context, versioned with the codeSpec-driven tooling made this the norm; SLICE must say what goes in it and how much7
5Verification capacity becomes the hard work-in-progress limitTelemetry shows review queues absorbing the coding gains9
6Forecast levels get minimum sample sizes; codebase type joins the reference classGains vary several-fold between greenfield and complex brownfield work8
7New metrics: decision latency, idea-to-evidence time, review wait, unreviewed merges, validated-outcome rateMeasure the bottleneck the framework claims exists11
8Explicit positioning against AWS AI-DLC, BMAD, Spec Kit and Shape UpProportional, AI-native process is no longer unique3
9C in SLICE now means Capacity-bound"Confidence-led" and "Evidence-driven" overlapped4
10Normative voice throughoutv0.1 reads as a reply to a person ("I agree with your observation") and carries interface leftovers ("Copy feature card")all

Kept from v0.1 unchanged: the five-level hierarchy, Now/Next/Later, the four item types, XS–XL sizing without hour equivalents, AI leverage as a forecast input rather than a discount, F0–F3 evidence labels, Direction/Target/Commitment, the conformance-rule approach and vendor neutrality.

On the research document: it is a good survey, with two corrections. METR's February 2026 update did not report a speedup; it reported that its new data was too biased to estimate one. And its illustrative day ranges and multiplier explorer should stay out of the spec; v0.1 was right to drop them.

1. The thesis, restated

Building is cheap. Deciding and proving are not. The founding claim, that knowing what to build and when is now the bottleneck, is right. But v0.1 answers it with "plan less", which only works once "planning" is split into three different kinds of work.

Kind of workWhat it isWhat AI did to itSLICE stance
CoordinationEstimating, ticket-writing, sequencing, status reporting, specs written for other humansCheaper, often unnecessary in small teamsMinimise. Budget it.
DecisionChoosing the user, the problem, the bet, the scope cut and the evidence that counts as doneUnchanged or harder: more options are now cheap to build, so more must be rejectedInvest deliberately. This is the new constraint.
ProofReview, verification, integration, release, and learning whether the shipped thing workedHarder: more code arrives faster than people can check itSize all work to this capacity.

v0.1 handles coordination well (the Planning Budget) and proof partly (section 5.6). It barely handles decision work, which is the part the thesis is actually about. v0.2 makes all three explicit.

Two consequences follow. First, when building is cheap, building becomes a planning tool: a throwaway prototype is often a cheaper way to resolve a decision than a document or a meeting. Second, the specification stops being paperwork for humans and becomes context for agents, so the right spec is worth more than before, while the wrong kind of planning is worth less.

2. Evidence base

The evidence supports "building is cheaper" only unevenly, strongly supports "proof is a bottleneck", and supports "deciding is the bottleneck" mostly through practitioner testimony. SLICE should say so plainly, and treat the third claim as the hypothesis its pilots must test.

SourceFindingImplication for SLICE
DORA 2025, ~5,000 professionalsAI amplifies an organisation's existing strengths and dysfunctions. AI adoption now correlates positively with throughput, but stability remains a problem. About 90% use AI; 30% report little or no trust in its output.Keep "AI is an execution resource, not a multiplier". Small batches and quality systems are prerequisites, not options.
METR RCT, early 2025Experienced developers on their own mature repos were 19% slower with AI, yet believed they were 20% faster.Self-reported speed is not evidence. SLICE forecasts only from measured, accepted delivery.
METR update, 24 Feb 2026New data unreliable: developers refused to work without AI, pay was cut, and multi-agent work broke time measurement. METR believes speedup is likely higher now but cannot size it; returning developers' estimate was still a slowdown with a wide interval.No credible universal speedup number exists. Teams must build their own reference classes.
Faros AI 2025, 10,000+ developers, 1,255 teams21% more tasks and 98% more PRs per developer, but review time +91%, PR size +154%, bugs +9%; company-level delivery flat.The gain leaks into review. Size slices to review capacity.
Faros AI 2026, 22,000 developers, 4,000+ teamsMedian time in review +441.5%; PRs merged with no review +31.3%; incidents per PR +242.7%.Track review wait and unreviewed merges as first-class metrics.
Stanford, Denisov-Blanch, ~100,000 developersGains of 30–35% on simple greenfield work, 5–10% on complex brownfield work; AI also adds rework.Codebase type must be part of every reference class. Greenfield history does not forecast brownfield work.
Andrew Ng, Stanford CS230Names the product-management bottleneck; engineer-to-PM ratios trending toward 1:1; one team proposed 1 PM to 0.5 engineers; "build 20 prototypes to see what works".Supports the thesis and the Build-to-decide mode. Note: this is expert testimony, not measurement.
Shape Up, BasecampAppetite is a time budget set before shaping; fixed time, variable scope.SLICE's appetite rule is borrowed; credit it.
Magennis via SEP; ProKanbanWith 7, 11 and 20 samples, the chance the next falls in the seen range is about 75%, 83% and 90%. Under six weeks of throughput is jittery; over 26 risks forecasting an old team.Gives F2 and F3 concrete entry thresholds.

The gap SLICE can fill: nobody has measured decision latency or idea-to-evidence time in AI-native teams. If SLICE pilots record them, the framework produces the first evidence for its own thesis. That is a stronger launch asset than the framework text.

3. Landscape and positioning

SLICE should be the decision and forecasting layer above spec-driven execution tools, not another execution method. Since mid-2025 several AI-native methods have shipped. All of them answer "how do we get agents to build this well". None answers "which slice, why, how much, by when, and did it work".

MethodWhat it isOverlap with SLICEWhere SLICE differs
AWS AI-DLC (Jul 2025)AI leads execution, humans hold decision rights. Inception, Construction and Operations phases; work in "Bolts" of hours or days; Mob Elaboration where the team validates AI-written requirements liveAI-native lifecycle, short cycles, human accountabilityAI-DLC adds ceremonies (mob sessions) and has no forecasting, commitment model or outcome kill criteria
BMAD Method (open source, MIT)Agent personas produce PRD, architecture and story files; three planning tracks scale process to complexityDirectly overlaps the planning modes and spec-as-contextBMAD is document-forward and tooling-bound; no roadmap, forecast or outcome loop
GitHub Spec Kit (Sep 2025)Spec, then plan, then small testable tasks for agents; a project "constitution"Spec as agent contextA tool for one feature. SLICE should recommend it for Mode 2–3 specs, not compete with it
Shape UpAppetite, shaping, betting, six-week cyclesAppetite and shapingSLICE runs continuous flow, adds forecasting and evidence levels
Kanban (ProKanban)Flow metrics, Monte Carlo forecastingFlow metrics and F3SLICE adds decision and outcome layers
XB Software Functional Slices (Jun 2026)Value breakdown plus "functional slices"; forecasts slice-days by multiplying a traditional estimate by AI-efficiency and exploration factorsSame unit, near-identical vocabularySLICE rejects multiplier estimates; this is a clean, citable contrast

Not distinctive (credit, do not claim): proportional process, vertical slices, appetite, flow metrics, spec-as-context.

Potentially distinctive (the five things to test):

  1. A Decision Budget that treats throwaway builds as a planning instrument.
  2. Verification capacity, not agent count, as the work-in-progress limit.
  3. Forecast evidence labels (F0–F3) tied to Direction / Target / Commitment for investors.
  4. Outcome hypotheses with kill criteria wired into the roadmap.
  5. Measuring decision latency and idea-to-evidence time.

Public line: "Use SLICE to decide and forecast. Use any spec tool to execute." Gojko Adzic's warning that spec-driven development could bring back waterfall rigidity is SLICE's opening: SLICE is the discipline that keeps specs small and tied to evidence.

4. Principles (revised)

Core line: "Decide deliberately. Build small. Count only what is proven." It replaces "Shape only what matters. Build in small slices. Forecast from evidence.", which said nothing about the decision bottleneck.

Letterv0.1v0.2Rule it creates
SStrategicStrategicEvery item traces to an outcome or an obligation.
LLightweightLightweight (coordination)Coordination effort is budgeted and minimised; decision effort is invested on purpose.
IIterativeIterativeOnly the next slice needs detail. Specs are living documents, updated when implementation teaches something.
CConfidence-ledCapacity-boundWork in progress is limited by human decision and verification capacity, never by the number of agents that can run.
EEvidence-drivenEvidence-drivenEvery estimate, date and outcome claim states its evidence level and confidence. Actuals replace assumptions.

Confidence moves into E, where it belonged. Capacity-bound is the principle the research most clearly supports, and the one most AI-era methods leave out.

5. SLICE Roadmapping (revised)

Every initiative in Now or Next becomes a Bet with a falsifiable outcome and a kill criterion. The hierarchy (Outcome → Initiative → Feature → Slice → Agent work), the Now/Next/Later horizons and the four item types stay as in v0.1.

5.1 The Bet

FieldRuleExample
Outcome hypothesis"If we ship X, metric Y moves from A to B within T."Self-serve checkout lifts trial-to-paid from 4% to 6% within 8 weeks of release
Hypothesis evidenceWhat the belief rests on today: opinion, interviews, prototype test, live data9 of 12 interviewed trial users asked to pay without a call
AppetiteThe capacity this bet is worth, set before shaping (from Shape Up)3 weeks of one builder's verified delivery
Leading indicatorA signal readable within 2 weeks of releaseCheckout starts per trial
Kill criterionThe result that stops or reverses the betUnder 5% trial-to-paid after 8 weeks, or checkout starts under 10% of trials after 2
Outcome review dateA fixed date, set at releaseRelease + 8 weeks

5.2 Changes to item types

  • Experiment now explicitly produces a decision, not software. Throwaway code is expected and is deleted or archived when the decision is made.
  • Delivery items are only "done" for the roadmap after their outcome review. Accepted delivery counts for forecasting; reviewed outcome counts for the roadmap.
  • Removal is a legitimate result. When building is cheap, unused features pile up faster; an outcome review that ends in removal is a success of the method, not a failure of the team.

5.3 Prioritisation: a fourth rule

v0.1's three rules stay (obligations first, rank by value, urgency and evidence, then set an appetite). Add: when two bets are close, take the one whose evidence arrives sooner. In an AI-native team, time to evidence is usually a better tiebreaker than effort, because effort differences have shrunk.

6. The Decision Budget (replaces the Planning Budget)

Cap coordination time; size decision time to the cost of being wrong; and when the open question is about value, build instead of debating. This is the mechanism that answers the founding thesis directly.

6.1 Modes

ModeUse whenOutputIllustrative time box
0 DirectReversible, obvious changeOne line of acceptance5 minutes
1 Slice briefBounded feature, known interfacesA Slice Card (section 10)15–30 minutes
B Build to decide (new)The open question is about value or usability: "should we", "which version"2–3 throwaway variants shown to users or the decider; one recorded decisionUp to 1 builder-day, then decide
2 Technical shapeArchitecture choices, migrations, dependenciesA short decision record plus a spike1–2 hours before the spike
3 Assured designSecurity, money, privacy, irreversible data, regulationReviewed design and test planRisk-governed, no ceiling

The time boxes remain starting policy, not established standards.

6.2 Choosing the mode

  1. Is the uncertainty about value (should we, which one) or about feasibility and risk (can we, safely)? Value → Mode B. Feasibility → Mode 2.
  2. How costly is reversal? If a mistake reaches customer money, data or trust, Mode 3 overrides everything.
  3. Otherwise use the lightest mode that leaves the stop rule answerable.

6.3 The stop rule (extended)

v0.1's four questions stay: the outcome or obligation, the smallest useful slice, the most consequential risk, and the evidence of completion. Add a fifth, a plain value-of-information test: would any realistic answer to the next open question change what we build? If not, stop planning and start.

6.4 Decision rights

Each Bet names one decider. Most decision latency comes from unclear decision rights, not missing information. Every decision is recorded in one line (what, why, who, date) in the repo, so humans and agents read the same record.

6.5 Measuring it

v0.1's Planning Overhead Ratio needs everyone to log planning effort, which few teams will do accurately. Replace it with two fields per slice: coordination minutes (estimated at close) and decision latency (time from a question being raised to its decision being recorded). The ratio can still be derived where data exists.

7. Specification as agent context (new)

Planning output must be readable by agents, not only by people, and it lives in the repository in three layers. An agent reads the repo and copies the patterns it finds, so stale or missing context becomes a defect, not a documentation gap.

LayerContentsChanges whenTypical home
Product contextTarget user, outcomes, glossary, constraints, non-negotiables, design-system rulesStrategy or constraints changeAGENTS.md, CLAUDE.md, a Spec Kit constitution
Decision logOne line per decision: what, why, who, dateEvery decision (section 6.4)docs/decisions
Slice specThe Slice Card plus acceptance evidence, written as tests where possibleEach slice; folded into tests on completionBeside the branch

Rules:

  • Spec size follows the mode: Mode 0 none; Mode 1 the card; Modes 2 and 3 add a decision record and test plan. A longer spec needs a stated reason.
  • Acceptance evidence is executable where possible. The test suite is the durable, machine-checkable form of the spec.
  • Living, not frozen: when implementation contradicts the spec, update the spec first, then continue. This is the line between spec-driven work and waterfall in markdown.
  • Every context file has an owner. Context older than the code it describes is flagged in review.
  • Any format conforms: Spec Kit, BMAD stories, plain markdown. SLICE specifies what must be present, not the tool.

8. SLICE Forecasting (revised)

Keep v0.1's model; add decision waiting time to the formula, codebase type to the reference class, and minimum evidence to each forecast level. Size, AI leverage, risk, F0–F3 and P50/P85/P95 stay as defined in v0.1.

8.1 Decision wait becomes visible

Tslice=Tactive+Treview and queue+Tdecision wait+Texternal waitT_{\text{slice}} = T_{\text{active}} + T_{\text{review and queue}} + T_{\text{decision wait}} + T_{\text{external wait}}

v0.1 hid decision waiting inside "queue" or "external". Separating it lets every forecast show how much of the delay is the bottleneck SLICE claims exists.

8.2 Reference classes

A reference class is the combination of size, work type, Decision Budget mode and codebase context (greenfield, established, legacy). The Stanford data shows gains several times larger on simple greenfield work than on complex brownfield work, so history from one context never forecasts another.

8.3 Minimum evidence per level

LevelMinimum evidenceAllowed output
F0None"Not estimated"
F1Expert judgment or analogyLabelled scenarios (optimistic / expected / conservative), never percentiles
F27 or more accepted slices in the same reference classObserved range of comparable slices; about 75% chance the next one falls inside it
F311–20 comparable items or 6+ weeks of throughput, from after the last major change, plus at least one back-tested forecastP50 / P85 / P95 from simulation

Thresholds follow Magennis's sampling guidance and ProKanban's history window.

8.4 Change resets

A major change in model or tool, team or codebase phase opens a new reference window. Old history becomes a prior, not a forecast basis, until the new window meets its level's minimum. AI tooling changes often enough that this rule will fire several times a year.

8.5 Two forecasts per Bet

Each Bet carries a delivery forecast (F-level) and a separate outcome forecast, which is usually F0 or F1. They are never merged into one confidence figure.

8.6 Non-conformant practice

Any estimate of the form "traditional estimate × AI efficiency factor" is non-conformant. Leverage informs the choice of reference class; it never scales a number.

9. Verification capacity is the WIP limit (new)

New agent work starts only when the verification queue has room. By Little's Law, average cycle time equals work in progress divided by throughput. If review caps throughput, launching more agents only raises WIP and lengthens cycle time, which is what the Faros telemetry shows.

  1. Declare capacity. State the human hours per week available for review, testing, acceptance and release decisions. Recalibrate monthly.
  2. Pull, not push. Slices awaiting or under verification may not exceed what that capacity clears in about one week. Above the limit, stop starting and finish.
  3. Reviewable slices. A slice must be reviewable in one sitting. Oversized diffs are split before review, not after. The 2025 data tied a 154% rise in PR size to a 91% rise in review time.
  4. Verification tier follows risk.
RiskMinimum verification
LowAutomated tests pass; agent review; human skim of the diff
MediumAutomated tests; full human review of the diff against acceptance evidence
High (Mode 3)Independent human review by someone who did not direct the agent; explicit approval for data, money or security changes
  1. Self-review is never independent. An agent's or author's own review counts as a check, not as assurance.
  2. No unreviewed merges above Low risk. The unreviewed-merge rate is reported every cycle (section 11).

10. Workflow, cadence and the Slice Card

The loop now starts and ends with decisions, and verification capacity gates every new build. v0.1's six steps (Strategy, Shaping, Forecasting, Execution, Acceptance, Learning) become the loop below.

[Diagram not reproduced in this archived version: SLICE v0.2 workflow · 6 steps, 1 WIP gate.]

Three of six steps are decision work and two are proof work; only Build got cheap, which is why it is the one step SLICE does not try to optimise.

10.1 Cadence

WhenWhatTime
ContinuousBuild, verify, release—
WeeklyFlow check: WIP against capacity, review wait, decisions open too long20 minutes
On each review dateOutcome review: keep, iterate or remove15 minutes per Bet
MonthlyBet review: new bets, kills, recalibrate capacity, check reference windows60 minutes
QuarterlyStrategy and investor updateHalf a day

No ceremony is mandatory; these are defaults for a team of up to about 25.

10.2 Slice Card v0.2

The v0.1 card gains a Bet link, the Decision Budget mode, the decider, the reference class, the verification tier and a close-out block. The close-out block is what turns daily work into forecasting history.

markdown
SLICE CARD · v0.2

Bet: Self-serve checkout (trial-to-paid 4% -> 6% within 8 weeks)
Slice: Test-mode checkout creates the correct entitlement after a confirmed payment
Mode: 3 (money)            Decider: founder
Size: L    Risk: High (consequence)    AI leverage: High
Reference class: L / integration / Mode 3 / established codebase
Acceptance evidence (as tests): successful, failed, delayed-webhook
  and duplicate-webhook payments
Primary uncertainty: webhook ordering and entitlement consistency
Verification: independent human review of payment and data changes
Forecast: 2-3 weeks · F1 scenario · Target
Open decisions: [question · owner · due]

Close-out (at acceptance): coordination minutes · decision latency ·
  cycle time · review wait · rework

11. Metrics (revised)

Measure each of the three bottlenecks, not only flow. v0.1 measured delivery well and decisions not at all. The six metrics marked mandatory are the minimum for a solo founder; the rest are for teams that need them.

BottleneckMetricDefinitionStatus
FlowAccepted throughputSlices accepted per week, by reference classKept, mandatory
FlowCycle timeStart to accepted completionKept, mandatory
FlowWIP and item ageItems in progress and how long each has been thereKept
DecisionDecision latencyQuestion raised to decision recordedNew, mandatory
DecisionIdea-to-evidence timeBet approved to first leading-indicator readingNew
DecisionCoordination minutesEstimated per slice at closeReplaces planning effort
ProofReview waitSlice ready to verification startedNew, mandatory
ProofUnreviewed-merge rateShare of merges with no human review, by risk tierNew
ProofRework and escaped defectsAs v0.1; add change failure rate from DORAKept
OutcomeValidated-outcome rateShare of reviewed Bets whose hypothesis heldNew, mandatory
OutcomeRemoval rateFeatures removed after outcome reviewNew
ForecastCalibrationShare of actuals inside the stated P85 (F3) or range (F2)Kept, mandatory

The v0.1 rule stands: none of these becomes an individual performance target. Validated-outcome rate is the one most likely to be gamed, by writing timid hypotheses, so hypotheses are reviewed for ambition at the betting step.

12. Scaling, commitments and investor communication

Narrow the scaling claim to teams of 1–25 until pilots show otherwise, and print the evidence level beside every date. v0.1's "solo founder to hundreds of engineers" is untested and invites the wrong first customers.

12.1 Scope of the v0.2 claim

SLICE v0.2 is specified for solo founders and teams up to about 25. The 25+ column from v0.1 moves to an appendix marked "untested". Enterprise programmes bring governance that a v0.2 framework cannot credibly specify yet.

AreaSolo / 2–56–25
Decision rightsFounder decides; decisions loggedOne decider per Bet, named on the card
Verification capacityDeclared weekly by the founderDeclared per team; review load shared, never pooled into a separate QA queue
ForecastingF1 scenarios until F2 thresholds are metF2 per reference class; F3 where history allows
ReviewsOutcome reviews on their dates; weekly 20-minute flow checkWeekly flow check; monthly bet review

12.2 Commitment rules (tightened)

  • Every external date shows its commitment type and evidence level, for example "Self-serve checkout · Target · Q1 · F1".
  • A Commitment requires F2 or better, or the decider's written acceptance of F1 risk.
  • Delivery dates and outcome forecasts are reported on separate lines, as in v0.1.

12.3 Investor update, one page

  1. Bets in Now and Next, each with its hypothesis and evidence level.
  2. Delivery: what was accepted, against the last update's targets.
  3. Outcomes: reviews completed this period, validated-outcome rate, removals.
  4. Forecast calibration: how the last period's targets compared with actuals.
  5. Changes: what moved and why.

13. Conformance rules v0.2

Ten rules; a team that follows all ten practises SLICE, whatever its tools. v0.1 had seven; the three additions cover decisions, verification capacity and outcomes.

A team practising SLICE must:

  1. Keep an outcome-connected roadmap with Now, Next and Later. Every Now and Next initiative is a Bet with a hypothesis, appetite, kill criterion and review date.
  2. Choose a Decision Budget mode for each slice, and record coordination minutes and decision latency.
  3. Name one decider per Bet, and log decisions in the repository.
  4. Keep product context, decision log and slice specs in the repository, each with an owner and current with the code.
  5. Split scheduled work into independently verifiable slices, each reviewable in one sitting; decompose XL before scheduling.
  6. Record size, dominant risk, AI leverage, reference class and forecast evidence level for each slice.
  7. Limit work in progress by declared verification capacity, with no unreviewed merges above Low risk.
  8. Label every date with its commitment type and evidence level. Never present judgment as percentiles; never scale an estimate by an AI factor.
  9. Count a slice as delivered only when its acceptance evidence passes, and a Bet as done only after its outcome review.
  10. Track the six mandatory metrics and use them to change plans.

Optional: tools, AI models, cadence, sprints, role names and prioritisation formula.

14. Validation plan and how SLICE could fail

Pilot it on three genuinely different products for eight weeks, with pass/fail thresholds written before the pilot starts. v0.1's three stages stay; v0.2 adds the hypotheses and the red team.

14.1 Pilot hypotheses (thresholds are proposals)

#HypothesisPasses if
H1The Decision Budget shortens decisionsMedian decision latency falls 30%+ from the first two weeks to the last two
H2Less coordination does not cost qualityCoordination minutes per slice fall while rework and change failure do not rise
H3Forecasts are calibrated70%+ of F2 actuals fall inside the stated range; F3 P85 dates are met 80–90% of the time
H4The outcome loop actually runs80%+ of Bets reach their outcome review on the planned date
H5The WIP rule protects reviewReview wait stays flat while accepted throughput rises

A solo pilot has no control group, so results are before/after evidence only. External pilots (5–10 teams of 1–25 people, 8–12 weeks) should compare against two to four weeks of each team's previous process.

14.2 Red team: how SLICE fails

  1. Measurement burden. Teams will not hand-log decision latency or coordination minutes. Mitigation: derive both from issue and repository timestamps; never require a timesheet.
  2. Outcome reviews get skipped once shipping feels good, the classic failure of OKR-style systems. Mitigation: the review date is set at release and a Bet cannot close without it.
  3. The card grows. Bet, Slice Card and reference class can recreate the overhead SLICE fights. Mitigation: if a Mode 1 card regularly takes over 30 minutes, cut fields.
  4. The bottleneck moves again. If AI review becomes trustworthy, verification capacity rises and decisions dominate even more. SLICE must measure capacity, never assume it.
  5. No moat in ideas. Every mechanism is copyable and overlaps BMAD, Shape Up and Kanban. Durable value comes from published pilot evidence, templates that live inside the tools teams already use, and a reputation for calibrated numbers.

15. Naming and clearance

Keep SLICE as the working name for pilots, but expect it to be hard to own; decide the public name after the pilots. The expansion becomes Strategic, Lightweight, Iterative, Capacity-bound, Evidence-driven Execution.

A web check found no existing methodology called "SLICE Framework", but the word is crowded in this exact space:

A common English word that also describes the core unit is weak as a trademark and poor in search. Before public launch: run EUIPO and USPTO searches in classes 9, 41 and 42, check domains, and test whether "SLICE" plus a distinctive qualifier is enough. The decision does not block pilots.

Sources